Five Year Capital Improvement Road Program (CIRP)
2025/2026 FY
Chino Drive
- From: Bosque Road
- To: Bowie Road
- Length: 0.25 mi.
- Activity: Soil stabilization and hard surfacing
- Estimated Cost: $75,000
- County project; estimate reflects surface and drainage improvements
Sand Hollow Bridge Reconstruction (Design)
- Activity: Strengthen bridge to remove load restriction
- Estimated Cost: $28,500
- $471,500 programmed federal funds (pending)
2026/2027 FY
Gold Springs Road and Blue Canyon Road Shoulder Widening (Construction)
- From-To: Eastern end
- Length: 0.54 mi.
- Activity: Widen to establish 3-foot shoulders and edge lines
- Estimated Cost: $17,361
- $287,226 programmed Federal funds
Pierce Ferry Road Rumble Strips (Construction)
- From: U.S. 93
- To: Lloyd Road
- Length: 5.7 mi.
- Activity: Centerline and edgeline rumble strips
- Estimated Cost: $0
- $492,591 programmed Federal funds
Stockton Hill Road Widening (Design)
- From: Red Wing Canyon Road
- To: Calle Lucero
- Length: 2.65 mi.
- Activity: Pavement and shoulder widening
- Estimated Cost: $17,232
- $285,088 programmed Federal funds (pending)
White Hills Road Shoulder Widening (Design)
- From: Mineral Road
- To: Skipper Boulevard
- Length: 2.36 mi.
- Activity: Pavement and shoulder widening
- Estimated Cost: $14,117
- $233,553 programmed Federal funds (pending)
London Bridge Road Widening and Pavement (Design)
- From: Clty/County North Limit
- To: Fathom Drive
- Length: 2.87 mi.
- Activity: Shoulder widening and high -friction pavement Design) treatment
- Estimated Cost: $11,837
- $195,833 programmed Federal funds (pending)
2027/2028 FY
Rancho Santa Fe Parkway
- From: Louise Avenue
- To: Hualapai Mountain Road
- Length: 2 mi.
- Activity: Construct two-lane roadway
- Estimated Cost: $6,500,000
- Coordinated with City of Kingman under planned I-40 Rancho Santa Fe Interchange
Egar Road
- From: Agua Fria
- To: Drive Chinle Drive
- Length: 2 mi.
- Activity: Soil stabilization and hard surfacing
- Estimated Cost: $900,000
- County project; activity contingent on local asphalt millings availability (need 5.09 acres private right-of-way)
Mountain View Road
- From: Courtwright Road
- To: Boundary Cone Road
- Length: 6 mi.
- Activity: Construct two-lane roadway
- Estimated Costs: $14,000, 000
- County project
Sand Hollow Bridge Reconstruction (Construction)
- Activity: Strengthen bridge to remove load restriction
- Estimated Cost: $0
- $4,300,000 programmed federal funds (pending)
Stockton Hill Road Widening (Construction)
- From: Red Wing Canyon Road
- To: Calle Lucero
- Length: 2.65 mi.
- Activity: Pavement and shoulder widening
- Estimated Cost: $261,289
- $4,322,726 programmed Federal funds (pending)
White Hills Road Shoulder Widening (Construction)
- From: Mineral Road
- To: Skipper Boulevard
- Length: 2.36 mi.
- Activity: Pavement and shoulder widening
- Estimated Cost: $224,466
- $3,713,528 programmed Federal funds (pending)
London Bridge Road Widening and Pavement (Construction)
- From: Clty/County North Limit
- To: Fathom Drive
- Length: 2.87 mi.
- Activity: Shoulder widening and high -friction pavement Design) treatment
- Estimated Cost: $121,162
- $2,004,480 programmed Federal funds (pending)
2028/2029 FY
Bank Street
- From: North Boundary Section 19
- To: Calle Castrano
- Length: 2 mi.
- Activity: Soil stabilization and hard surfacing
- Estimated Cost:$1,560,000
- County project; estimate reflects surface and drainage improvements (need 10.18 acres State and 0.5 acres Private right-of-way)
2029/2030 FY
Vanderslice Road
- From: Laguna Road
- To: Sterling Road
- Length: 11 mi.
- Activity:Construct and widen/reconstruct
- Estimated Cost: $95,000,000
- Identify, funding mechanism ( Courtwright to Laguna - 2020- 21 roller compacted concrete reconstruction; estimate reflects 2008 DCR estimate escalated by 2008 Q2 to 2024 Q3 National Highway Construction Cost Index plus $ 10M design)